Opening the Doors to Receivership Success: A Roundtable Discussion
6/6/2012 Articles
Receivers Roundtable Presentation Outline
Receivership Sale Issues
- CCP 568.5: “A receiver may, pursuant to an order of the court, sell real or personal property in the receiver's possession upon the notice and in the manner prescribed by Article 6 (commencing with Section 701.510) of Chapter 3 of Division 2 of Title 9. The sale is not final until confirmed by the court.”
- Courts vary on whether they will authorize sale of receivership property based on this statute and interpretive case law.
- Some courts require compliance with execution sale procedures
- Some title insurance companies require consent of borrower (defendant) and/or lien holders
Mechanics’ Lien Issues
- Civil Code
- Until 7-1-12, Civil Code 3082 to 3152
- After 7-1-12, Civil Code 8000 to 956
- Intent of changes to Civil Code
- Simplify and standardize
- Be non-substantive
- Clarify terminology
- Preliminary notice
- Direct contractor required notice to construction lender only
- Subcontractors required notice to owner, direct contractor and lender
- Must use new Waiver and Release Forms
- Progress payment exclusions
- Retention
- Extras
- Identified progress payments remaining unpaid
- Contract rights
- Progress payment exclusions
- Notice of completion by owner increased to 15 days to record
- Mechanics lien release bonds reduced to 125% of the lien amount
- Direct contractor must record lien
- 90 days after completion
- 60 days after recording notice of completion or cessation
- Parties other than a direct contractor must record lien
- After claimant ceases to provide work
- 90 days after completion
- 30 days after recording notice of completion or cessation
- Amount of lien is the lesser amount of reasonable value or amount agreed to be paid
- Petition for release of stale lien
- Hearing within 30 days of filing and Order within 60 days of filing
- Prevailing party is now entitled to reasonable attorneys’ fees Panelists
- Petition for release of stale lien
Purchaser/Vendor Lien Issues
- Civil Code Section 3046: “One who sells real property has a vendor’s lien thereon, independent of possession, for so much of the price as remains unpaid and unsecured otherwise than by the personal obligation of the buyer.”
- Civil Code Section 3050: “One who pays to the owner any part of the price of real property, under an agreement for the sale thereof, has a special lien upon the property, independent of possession, for such part of the amount paid as he may be entitled to recover back, in case of a failure of consideration.”
- Civil Code Section 3048: “The liens defined in Sections 3046 and 3050 are valid against every one claiming under the debtor, except a purchaser or encumbrancer in good faith and for value.”
- Lien of purchaser of condo or holder of similar interest may have priority over secured lender if lender aware of their interest
- Lien priority issues should be resolved prior to receivership property sale
Environmental Issues
- Powerful tool to deal with environmental contamination and/or ongoing compliance/permitting issues
- Primary advantage: lenders can sell, cleanup or otherwise rectify environmental problems without loan foreclosure, i.e., no mortgagee in possession, but security interest in the property is protected
- Receiver’s scope granted by Court’s authority is key, and can be modified over time
- Receiver has quasi-judicial immunity
- Potential exception: In re Sundance Corp., 149 B.R. 641 (Bankr. E.D. Wash. 1993); cf. Gregory vs. U.S., 942 F.2d 1498 (10th Cir. 1991)
- Receiver needs own environmental attorney and consultant to advise on legal requirements, options and creative fixes.
- Receiver can also sell the property with warts and all, with “clean title” but:
- Certain liabilities – ongoing permitting or compliance issues, site contamination issues posing risks to human health and the environment will not be “scrubbed out”
- Buyer beware – “as is” sale with no meaningful representations or warranties provided
- Conduct due diligence including talk to regulators
- Potential for fix or delay
- Other environmental and safety risk mitigation options
- Buy environmental insurance (Pollution Legal Liability or PLL)
- Request or provide indemnities with real value
- Engage regulators with creative, site/project specific options
- Landlord’s potential liabilities left by “underwater tenant”
- Consider actions that limit imminent threats to health, safety and the environment so that landlord’s potential liability does not expand
Property Management Agreement Issues
- Receiver’s potential termination of “branded” management agreement
- California Rule of Court 3.1179(b) – Receiver cannot enter into agreement with plaintiff/lender regarding receiver’s role following foreclosure sale or receivership termination without court approval.
- Receiver must ensure impartiality (as officer of the court) and not be perceived as beholden to secured lender (plaintiff) or any other party